RAUVILLE

Rauville Raw Water Transmission Pipeline - Watertown, SD

As part of the increasing demand for water, Belair Excavating received a contract to install a 24” water transmission main from the existing water treatment plant to the site of Watertown’s new Wellfield. A project totaling over 39,000 feet, crossing roads, streams and a mile of swamp land all within the 50 foot right of way. Despite the tough soil conditions and the record setting rain events that caused local flooding, Belair completed the work as scheduled.

Owner: Watertown Municipal Utilities

Contractor: Belair Excavating

Project Facts:

  • 39,000 LF of 24” Ductile Iron Pipe

  • 5 - 24” Gate Valves

  • Over 24,000 LBS of Fittings

  • 8 - Air/Vacuum Release Structures

  • 260 LF of 36” Cased Bore

  • 1,040 LF of Directionally Drilled 24” DIP

  • 2 - Blow-off Assemblies

  • 23,940 LF of Dewatering