Belair was contracted to complete the Civil portion of a petroleum rail loading facility and a truck ethanol unloading rack. The work involved in this project included the layout, excavation, concrete foundations and slabs, structural steel pipe stands and catwalks. Belair also installed operator buildings, equipment buildings and trucker shelters. The project was a renovation to an existing facility and required the work to be accomplished near and around active and abandoned pipes, conduits and grounding systems. Pipe supports ranged from 4 feet above grade to 22 feet above grade. Also installed was a storm water system including a 15,000 gallon separator tank.

Owner: Magellan Midstream Partners

Contractor: Belair Builders, Inc.

Project Facts:

  • Installed 195 Concrete Piers

  • Installed 21 different types of pipe stands or 87 individual stands

  • Poured 350 cubic yards of concrete with 11 tons of steel rebar

  • Removed 800 feet of abandoned pipelines

  • Excavated & Land-farmed 1,000 CY of soil

Previous
Previous

Lincoln Commons

Next
Next

Land Port of Entry